Batesville city employees will receive retention incentive pay this holiday season following a decision by the City Council during its meeting on Tuesday. Replacing the previous annual “Christmas bonus,” the approved payments will include $1,000 for full-time employees who worked at least 1,000 hours in 2026, $500 for those who worked 500 to 999 hours, and $250 for those who worked 100 to 499 hours. Permanent part-time employees will receive $500, $250, or $125 for the same respective hour thresholds. The incentive payouts will cost the city approximately $163,000, officials said.

Tuesday’s meeting also included updates from Michael McDaniel, superintendent of the city’s wastewater treatment plant, and Brice Barnes, assistant superintendent of the water treatment plant. The presentations were part of Mayor Rick Elumbaugh’s ongoing initiative to bring department leaders before the council to provide operational updates.

McDaniel detailed operations of the city’s wastewater treatment facility, which employs 10 full-time staff members, four of whom have worked there for more than 30 years. With a treatment capacity of 9 million gallons per day (MGD), the plant averaged 6.16 MGD in 2025 but has so far averaged 4.25 MGD this year. McDaniel highlighted the plant’s preventative maintenance efforts, noting that maintaining aging equipment is key to avoiding costly breakdowns. The plant, which went into operation in 2016, continuously treats wastewater through settling ponds, aeration basins, and advanced chemical processes to ensure compliance with state and federal standards.

McDaniel added that staff monitor flow rates, chemical feed systems, and equipment like screw pumps and bioreactors 24/7. He is optimistic about future upgrades, including an aeration system designed to address odor issues in the ponds, which he said have grown increasingly important as the city continues to expand.

Barnes reported on the operations of the city’s water treatment facility, which is staffed by 12 full-time employees and runs year-round. Originally designed with a capacity of 12.1 MGD over 60 years ago, the plant is nearing its operational limits. A new 15 MGD treatment plant and intake system is under construction to meet increasing demand and to replace aging infrastructure, he said.

Despite the challenges of maintaining equipment such as water intake structures and pump stations, Barnes emphasized that the facility continues to produce high-quality potable water, reporting average turbidity levels of 0.027 NTU (well below the EPA standard of 0.3 NTU). Last year, the water plant treated 2.3 billion gallons, and it is on pace to treat 2.7 billion gallons this year.

In other business, Mayor Elumbaugh introduced the city's new finance director, Sam Thapa, who recently moved to Batesville. Originally from Nepal, Thapa graduated in 2020 with a degree in accounting and previously lived in Michigan.

The council also approved amendments to the 2025 General Fund and Street Fund budgets to reflect higher expenditures due to unforeseen costs and lower-than-expected revenues. The administration is currently focused on drafting the 2027 budget, with a planning meeting scheduled for December 7. Rising fuel costs and inflation are anticipated to continue posing challenges for city budgets in the coming year, Elumbaugh noted.

The council went into executive session to discuss personnel matters. No action was taken, and no public comments were made during the meeting. Alderman Kyle Christopher was absent from the session.